  "section": "projects",
  "asOf": "2026-11-05",
  "method": "The 10 largest city capital projects, ranked by the largest current official dollar figure for each one: the city's own cost estimate where it published one, otherwise the money approved so far. Figures come from the city's adopted budget books, its audited financial report and its October 2026 quarterly project reports.",
  "projects": [
    {
      "rank": 1,
      "name": "North Water Reclamation Facility",
      "description": "A new wastewater treatment plant in north Cape Coral (phase 1, 8 million gallons a day). Commissioning is targeted for December 2030.",
      "department": "Utilities",
      "status": "In design. Design and construction-manager contracts are being negotiated.",
      "figures": [
        {
          "label": "City cost estimate",
          "amount": 400000000,
          "note": "Utilities quarterly report, October 15, 2026",
          "source": {
            "title": "City of Cape Coral, Utilities FY2026 CIP 4th Quarter Update",
            "short": "Utilities quarterly report",
            "url": "https://www.capecoral.gov/Documents/Departments/Office%20of%20Communications/quarterlyreports/fy26/q4/2026%2010%2015%20UTILITIES%204TH%20QTR%20CIP%20QUARTERLY%20UPDATES%20Final.pdf",
            "asOf": "2026-10-15",
            "page": "slide 2"
          }
        },
        {
          "label": "FY2027 proposed budget amount",
          "amount": 400000000,
          "source": {
            "title": "City of Cape Coral, FY 2027-2029 Proposed Budget",
            "short": "FY2027 proposed budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202027%20Proposed%20Budget%20for%20Digital%20Final%20V1.pdf",
            "asOf": "2026-07-23",
            "page": "266"
          }
        },
        {
          "label": "Money approved so far (design)",
          "amount": 7310782,
          "note": "Through September 30, 2025, from the city's table of ongoing capital projects",
          "source": {
            "title": "City of Cape Coral, FY 2026-2028 Adopted Budget",
            "short": "FY2026 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202026%20Adopted%20Budget%20for%20website.pdf",
            "asOf": "2025-09-25",
            "page": "360"
          }
        },
        {
          "label": "Spent",
          "amount": 322733,
          "note": "As of September 30, 2025",
          "source": {
            "title": "City of Cape Coral, Annual Comprehensive Financial Report, year ended September 30, 2025, Note 10 Construction Commitments",
            "short": "2025 audited financial report",
            "url": "https://www.capecoral.gov/Documents/Document%20Hub/Accounting%20Documents/Financial%20Reports/City%20of%20Cape%20Coral%202025%20ACFR%20Secure.pdf",
            "asOf": "2025-09-30",
            "page": "99 (printed page 80)"
          }
        }
      ],
      "compare": {
        "kind": "none",
        "text": "Too early to compare: no construction contract has been signed."
      }
    },
    {
      "rank": 2,
      "name": "North 3 Utilities Extension Program",
      "description": "Water, sewer and irrigation lines, plus stormwater, road and fiber work, for the North 3 neighborhood area.",
      "department": "Utilities",
      "status": "On hold. Design is 100% complete; on October 14, 2026 a Committee of the Whole put the project on hold to rebid it.",
      "figures": [
        {
          "label": "Money approved so far",
          "amount": 379661922,
          "note": "$59,889,885 approved through September 30, 2025, plus $319,772,037 in the FY2026 adopted budget",
          "source": {
            "title": "City of Cape Coral, FY 2026-2028 Adopted Budget",
            "short": "FY2026 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202026%20Adopted%20Budget%20for%20website.pdf",
            "asOf": "2025-09-25",
            "page": "360, 425"
          }
        },
        {
          "label": "FY2027 proposed addition",
          "amount": 37078189,
          "note": "Water, sewer and irrigation",
          "source": {
            "title": "City of Cape Coral, FY 2027-2029 Proposed Budget",
            "short": "FY2027 proposed budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202027%20Proposed%20Budget%20for%20Digital%20Final%20V1.pdf",
            "asOf": "2026-07-23",
            "page": "266"
          }
        },
        {
          "label": "Spent",
          "amount": 8836123,
          "note": "From the same table; the table does not print an as-of date",
          "source": {
            "title": "City of Cape Coral, FY 2026-2028 Adopted Budget",
            "short": "FY2026 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202026%20Adopted%20Budget%20for%20website.pdf",
            "asOf": "2025-09-25",
            "page": "360"
          }
        },
        {
          "label": "Design contract",
          "amount": 17320301,
          "source": {
            "title": "City of Cape Coral, Public Works FY26 Quarterly Update (July to September 2026)",
            "short": "Public Works quarterly report",
            "url": "https://www.capecoral.gov/Documents/Departments/Office%20of%20Communications/quarterlyreports/fy26/q4/2026-FY%2026%20Quarterly%20Update%20-July,%20August,%20September.pdf",
            "asOf": "2026-09-30",
            "page": "slide 32"
          }
        }
      ],
      "compare": {
        "kind": "none",
        "text": "No final budget to compare yet: the project is being rebid."
      }
    },
    {
      "rank": 3,
      "name": "North 1 West Utilities Extension Program",
      "description": "Six construction contracts that brought water, sewer and irrigation lines to the North 1 West area, plus Master Pump Station 720.",
      "department": "Utilities",
      "status": "Complete. Contract closeout is in process.",
      "figures": [
        {
          "label": "Money approved so far",
          "amount": 271371090,
          "note": "Through September 30, 2025, from the city's table of ongoing capital projects",
          "source": {
            "title": "City of Cape Coral, FY 2026-2028 Adopted Budget",
            "short": "FY2026 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202026%20Adopted%20Budget%20for%20website.pdf",
            "asOf": "2025-09-25",
            "page": "360"
          }
        },
        {
          "label": "Spent",
          "amount": 216752892,
          "note": "As of September 30, 2025, with $20,804,859 still committed under contracts",
          "source": {
            "title": "City of Cape Coral, Annual Comprehensive Financial Report, year ended September 30, 2025, Note 10 Construction Commitments",
            "short": "2025 audited financial report",
            "url": "https://www.capecoral.gov/Documents/Document%20Hub/Accounting%20Documents/Financial%20Reports/City%20of%20Cape%20Coral%202025%20ACFR%20Secure.pdf",
            "asOf": "2025-09-30",
            "page": "99 (printed page 80)"
          }
        },
        {
          "label": "Six construction contracts, combined",
          "amount": 201671500,
          "note": "The city marks each of the six contracts 'On Budget'",
          "source": {
            "title": "City of Cape Coral, Public Works FY26 Quarterly Update (July to September 2026)",
            "short": "Public Works quarterly report",
            "url": "https://www.capecoral.gov/Documents/Departments/Office%20of%20Communications/quarterlyreports/fy26/q4/2026-FY%2026%20Quarterly%20Update%20-July,%20August,%20September.pdf",
            "asOf": "2026-09-30",
            "page": "slides 20-27"
          }
        },
        {
          "label": "Amount approved a year earlier",
          "amount": 93019203,
          "note": "FY2025 table of ongoing capital projects",
          "source": {
            "title": "City of Cape Coral, FY 2025-2027 Adopted Budget",
            "short": "FY2025 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FINAL%20FY25%20Budget%20Book%20GFOA.pdf",
            "asOf": "2024-10-02",
            "page": "345"
          }
        }
      ],
      "compare": {
        "kind": "city",
        "text": "The city reports each of the six construction contracts as on budget. No official final total cost has been published yet."
      }
    },
    {
      "rank": 4,
      "name": "North 1 East Utilities Extension Program",
      "description": "Water, sewer and irrigation lines for the North 1 East area, including a booster pump station, storage tanks and the NE 24th Avenue contract.",
      "department": "Utilities",
      "status": "Under construction. Contracts awarded November 19, 2025; completion expected at the end of 2027.",
      "figures": [
        {
          "label": "Money approved so far",
          "amount": 226169231,
          "note": "Through September 30, 2025, from the city's table of ongoing capital projects",
          "source": {
            "title": "City of Cape Coral, FY 2026-2028 Adopted Budget",
            "short": "FY2026 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202026%20Adopted%20Budget%20for%20website.pdf",
            "asOf": "2025-09-25",
            "page": "360"
          }
        },
        {
          "label": "Contracts awarded to date",
          "amount": 112917214.5,
          "source": {
            "title": "City of Cape Coral, Public Works FY26 Quarterly Update (July to September 2026)",
            "short": "Public Works quarterly report",
            "url": "https://www.capecoral.gov/Documents/Departments/Office%20of%20Communications/quarterlyreports/fy26/q4/2026-FY%2026%20Quarterly%20Update%20-July,%20August,%20September.pdf",
            "asOf": "2026-09-30",
            "page": "slides 28-31"
          }
        },
        {
          "label": "Spent",
          "amount": 7209653,
          "note": "As of September 30, 2025",
          "source": {
            "title": "City of Cape Coral, Annual Comprehensive Financial Report, year ended September 30, 2025, Note 10 Construction Commitments",
            "short": "2025 audited financial report",
            "url": "https://www.capecoral.gov/Documents/Document%20Hub/Accounting%20Documents/Financial%20Reports/City%20of%20Cape%20Coral%202025%20ACFR%20Secure.pdf",
            "asOf": "2025-09-30",
            "page": "99 (printed page 80)"
          }
        },
        {
          "label": "Amount approved a year earlier",
          "amount": 165500535,
          "note": "FY2025 table of ongoing capital projects",
          "source": {
            "title": "City of Cape Coral, FY 2025-2027 Adopted Budget",
            "short": "FY2025 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FINAL%20FY25%20Budget%20Book%20GFOA.pdf",
            "asOf": "2024-10-02",
            "page": "345"
          }
        }
      ],
      "compare": {
        "kind": "none",
        "text": "Under construction. The city's own estimate is a rounded $250 million, so no exact comparison is possible yet."
      }
    },
    {
      "rank": 5,
      "name": "Parks and Recreation bond program",
      "description": "The voter-approved 2018 parks bond program: Festival Park, Yellow Fever Creek, Crystal Lake, Tropicana and other parks.",
      "department": "Parks and Recreation",
      "status": "Under construction. Festival Park and Yellow Fever Creek are 99% complete; Lake Meade is in design.",
      "figures": [
        {
          "label": "Money approved so far",
          "amount": 89786164,
          "note": "Through September 30, 2025, from the city's table of ongoing capital projects",
          "source": {
            "title": "City of Cape Coral, FY 2026-2028 Adopted Budget",
            "short": "FY2026 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202026%20Adopted%20Budget%20for%20website.pdf",
            "asOf": "2025-09-25",
            "page": "358"
          }
        },
        {
          "label": "Spent",
          "amount": 71949908,
          "note": "From the same table; the table does not print an as-of date",
          "source": {
            "title": "City of Cape Coral, FY 2026-2028 Adopted Budget",
            "short": "FY2026 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202026%20Adopted%20Budget%20for%20website.pdf",
            "asOf": "2025-09-25",
            "page": "358"
          }
        },
        {
          "label": "Festival Park budget",
          "amount": 17829987,
          "source": {
            "title": "City of Cape Coral, Public Works FY26 Quarterly Update (July to September 2026)",
            "short": "Public Works quarterly report",
            "url": "https://www.capecoral.gov/Documents/Departments/Office%20of%20Communications/quarterlyreports/fy26/q4/2026-FY%2026%20Quarterly%20Update%20-July,%20August,%20September.pdf",
            "asOf": "2026-09-30",
            "page": "slide 51"
          }
        },
        {
          "label": "Festival Park contract, as amended November 19, 2025",
          "amount": 18370218,
          "source": {
            "title": "City of Cape Coral, Public Works FY26 Quarterly Update (July to September 2026)",
            "short": "Public Works quarterly report",
            "url": "https://www.capecoral.gov/Documents/Departments/Office%20of%20Communications/quarterlyreports/fy26/q4/2026-FY%2026%20Quarterly%20Update%20-July,%20August,%20September.pdf",
            "asOf": "2026-09-30",
            "page": "slide 51"
          }
        }
      ],
      "compare": {
        "kind": "over",
        "amount": 540231,
        "text": "Festival Park: the amended contract is $540,231 more than that park's budget. The program as a whole has spent less than the money approved so far."
      }
    },
    {
      "rank": 6,
      "name": "Southwest Water Reclamation Facility improvements",
      "description": "Headworks expansion and filter work at the Southwest wastewater plant, plus a raw water main extension.",
      "department": "Utilities",
      "status": "Design complete; bid documents are being prepared. Construction completion is scheduled for September 2029.",
      "figures": [
        {
          "label": "Money approved so far",
          "amount": 59924473,
          "note": "$6,924,473 through September 30, 2025, plus $53,000,000 in the FY2026 adopted budget",
          "source": {
            "title": "City of Cape Coral, FY 2026-2028 Adopted Budget",
            "short": "FY2026 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202026%20Adopted%20Budget%20for%20website.pdf",
            "asOf": "2025-09-25",
            "page": "427"
          }
        },
        {
          "label": "City cost estimate",
          "amount": 51600000,
          "note": "October 15, 2026; may not cover the same scope as the approved amount",
          "source": {
            "title": "City of Cape Coral, Utilities FY2026 CIP 4th Quarter Update",
            "short": "Utilities quarterly report",
            "url": "https://www.capecoral.gov/Documents/Departments/Office%20of%20Communications/quarterlyreports/fy26/q4/2026%2010%2015%20UTILITIES%204TH%20QTR%20CIP%20QUARTERLY%20UPDATES%20Final.pdf",
            "asOf": "2026-10-15",
            "page": "slide 11"
          }
        },
        {
          "label": "Spent",
          "amount": 2368655,
          "note": "As of September 30, 2025",
          "source": {
            "title": "City of Cape Coral, Annual Comprehensive Financial Report, year ended September 30, 2025, Note 10 Construction Commitments",
            "short": "2025 audited financial report",
            "url": "https://www.capecoral.gov/Documents/Document%20Hub/Accounting%20Documents/Financial%20Reports/City%20of%20Cape%20Coral%202025%20ACFR%20Secure.pdf",
            "asOf": "2025-09-30",
            "page": "99 (printed page 80)"
          }
        }
      ],
      "compare": {
        "kind": "none",
        "text": "Not yet bid, so there is no contract to compare against."
      }
    },
    {
      "rank": 7,
      "name": "North reverse-osmosis water plant expansion and storage tank",
      "description": "Phase II expansion of the north drinking water plant (6 million gallons a day) and a new 12-million-gallon storage tank.",
      "department": "Utilities",
      "status": "In design; design completion March 2027. The city reports the project 'on budget'.",
      "figures": [
        {
          "label": "City cost estimate",
          "amount": 55400000,
          "source": {
            "title": "City of Cape Coral, Utilities FY2026 CIP 4th Quarter Update",
            "short": "Utilities quarterly report",
            "url": "https://www.capecoral.gov/Documents/Departments/Office%20of%20Communications/quarterlyreports/fy26/q4/2026%2010%2015%20UTILITIES%204TH%20QTR%20CIP%20QUARTERLY%20UPDATES%20Final.pdf",
            "asOf": "2026-10-15",
            "page": "slide 3"
          }
        },
        {
          "label": "Money approved through FY2026",
          "amount": 46947207,
          "note": "$5,525,527 through September 30, 2025, plus $41,421,680 in the FY2026 adopted budget",
          "source": {
            "title": "City of Cape Coral, FY 2026-2028 Adopted Budget",
            "short": "FY2026 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202026%20Adopted%20Budget%20for%20website.pdf",
            "asOf": "2025-09-25",
            "page": "428"
          }
        },
        {
          "label": "FY2027 proposed addition",
          "amount": 8500000,
          "source": {
            "title": "City of Cape Coral, FY 2027-2029 Proposed Budget",
            "short": "FY2027 proposed budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202027%20Proposed%20Budget%20for%20Digital%20Final%20V1.pdf",
            "asOf": "2026-07-23",
            "page": "266"
          }
        },
        {
          "label": "Spent",
          "amount": 382219,
          "note": "As of September 30, 2025",
          "source": {
            "title": "City of Cape Coral, Annual Comprehensive Financial Report, year ended September 30, 2025, Note 10 Construction Commitments",
            "short": "2025 audited financial report",
            "url": "https://www.capecoral.gov/Documents/Document%20Hub/Accounting%20Documents/Financial%20Reports/City%20of%20Cape%20Coral%202025%20ACFR%20Secure.pdf",
            "asOf": "2025-09-30",
            "page": "99 (printed page 80)"
          }
        }
      ],
      "compare": {
        "kind": "city",
        "text": "The city reports the project on budget (Utilities quarterly report, October 15, 2026)."
      }
    },
    {
      "rank": 8,
      "name": "US 41 utility pipeline (ADM-56)",
      "description": "A utility pipeline project along the US 41 corridor, paid for by water and sewer fees and federal grants.",
      "department": "Utilities",
      "status": "Under construction (84% complete in the FY2026 budget table).",
      "figures": [
        {
          "label": "Money approved so far",
          "amount": 51221990,
          "note": "Through September 30, 2025, from the city's table of ongoing capital projects",
          "source": {
            "title": "City of Cape Coral, FY 2026-2028 Adopted Budget",
            "short": "FY2026 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202026%20Adopted%20Budget%20for%20website.pdf",
            "asOf": "2025-09-25",
            "page": "360"
          }
        },
        {
          "label": "Spent",
          "amount": 42892888,
          "note": "As of September 30, 2025, with $1,605,913 still committed under contracts",
          "source": {
            "title": "City of Cape Coral, Annual Comprehensive Financial Report, year ended September 30, 2025, Note 10 Construction Commitments",
            "short": "2025 audited financial report",
            "url": "https://www.capecoral.gov/Documents/Document%20Hub/Accounting%20Documents/Financial%20Reports/City%20of%20Cape%20Coral%202025%20ACFR%20Secure.pdf",
            "asOf": "2025-09-30",
            "page": "99 (printed page 80)"
          }
        },
        {
          "label": "Amount approved a year earlier",
          "amount": 11221990,
          "note": "FY2025 table of ongoing capital projects",
          "source": {
            "title": "City of Cape Coral, FY 2025-2027 Adopted Budget",
            "short": "FY2025 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FINAL%20FY25%20Budget%20Book%20GFOA.pdf",
            "asOf": "2024-10-02",
            "page": "345"
          }
        }
      ],
      "compare": {
        "kind": "none",
        "text": "Still under construction, so there is no final cost yet."
      }
    },
    {
      "rank": 9,
      "name": "Bimini Basin East",
      "description": "City purchase, demolition and redevelopment of about 22 acres next to Bimini Basin in south Cape Coral.",
      "department": "Government Services",
      "status": "Demolition completed June 2025. Development agreements went to a final public hearing on October 21, 2026.",
      "figures": [
        {
          "label": "Money approved so far",
          "amount": 42059143,
          "note": "Through September 30, 2025, from the city's table of ongoing capital projects",
          "source": {
            "title": "City of Cape Coral, FY 2026-2028 Adopted Budget",
            "short": "FY2026 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202026%20Adopted%20Budget%20for%20website.pdf",
            "asOf": "2025-09-25",
            "page": "358"
          }
        },
        {
          "label": "Spent",
          "amount": 45192274,
          "note": "From the same table; the table does not print an as-of date",
          "source": {
            "title": "City of Cape Coral, FY 2026-2028 Adopted Budget",
            "short": "FY2026 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202026%20Adopted%20Budget%20for%20website.pdf",
            "asOf": "2025-09-25",
            "page": "358"
          }
        }
      ],
      "compare": {
        "kind": "over",
        "amount": 3133131,
        "text": "Spending in the city's table is $3,133,131 more than the money approved in the same table. The city has not published a breakdown of the spending or a total redevelopment budget."
      }
    },
    {
      "rank": 10,
      "name": "Community Resilience Hub",
      "description": "A planned community center at Festival Park that will double as a disaster shelter, paid for mostly by a Hurricane Ian recovery grant.",
      "department": "Public Works",
      "status": "In design. Design began January 5, 2026.",
      "figures": [
        {
          "label": "Money approved so far",
          "amount": 35441890,
          "note": "Through September 30, 2025, from the city's table of ongoing capital projects",
          "source": {
            "title": "City of Cape Coral, FY 2026-2028 Adopted Budget",
            "short": "FY2026 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202026%20Adopted%20Budget%20for%20website.pdf",
            "asOf": "2025-09-25",
            "page": "359"
          }
        },
        {
          "label": "Federal recovery grant (CDBG-DR)",
          "amount": 29904200.18,
          "source": {
            "title": "City of Cape Coral, CDBG-DR program",
            "short": "City grant page",
            "url": "https://www.capecoral.gov/department/emergencymanagementresilience/cdbg-dr.php",
            "asOf": "2026-11-05"
          }
        },
        {
          "label": "Spent",
          "amount": 20195,
          "note": "From the same table; the table does not print an as-of date",
          "source": {
            "title": "City of Cape Coral, FY 2026-2028 Adopted Budget",
            "short": "FY2026 adopted budget",
            "url": "https://www.capecoral.gov/Documents/Departments/Financial%20Services/Office%20of%20Management%20and%20Budget/FY%202026%20Adopted%20Budget%20for%20website.pdf",
            "asOf": "2025-09-25",
            "page": "359"
          }
        }
      ],
      "compare": {
        "kind": "none",
        "text": "Still in design, so there is no construction contract to compare against."
      }
    }
  ],
  "gaps": [
    "No official original, council-approved total cost was found for any of these 10 projects, so none can be called over or under its original budget. 'Money approved so far' is what the council has appropriated to date, not the full cost.",
    "The 'Spent' column in the city's FY2026 table of ongoing projects has no as-of date. Where the audited financial report gives spending at September 30, 2025, that figure is shown instead.",
    "The FY2027 adopted budget book was not posted on the city's budget page as of November 5, 2026, so there is no newer official project table.",
    "Council agenda packets were not yet searched for original contract values and change orders.",
    "North 1 West and North 1 East: the city's '$250 million' labels are rounded and are not used as budgets here.",
    "North 3 is on hold for a rebid; its budget is expected to change.",
    "Yacht Club reconstruction: no official total cost found ($15,402,112 approved and $5,985,530 spent in the FY2026 table; the city says council has not chosen a funding source). Not ranked.",
    "Emergency Operations Center (about $35 million estimate) and Everest Headworks Replacement ($31.5 million estimate) fall just outside the top 10. Recurring programs such as road resurfacing are not counted as single projects."
  ]
}